Progress – April 2018

Written by John Hillman

On April 30, 2018

April 2018

Crane Island Progress Blog
 

 

 

Crane Island – Amelia Island Florida – April 2018 Progress Blog

Over the past few months, we’ve been busy working diligently on a whole slew of things and we wanted to share some of this very good news with you!  

  • We’ve completed all Phase 1 infrastructure and we anticipate final land plat recording to occur May 14th, which then gives our Residents and Builders the green light to begin construction of their homes!

  • Major site work has begun on our River House/pool deck amenities and a small mountain has formed for as the views are amazing! it’s foundation, which we affectionally call “Mount Crane”.  See below 

  • We are well underway with Phase 2 infrastructure, adding 66 additional homesites and anticipate completion of that effort by the late Fall 2018. 

  • We have finalized our selection of 4 amazing Custom Home Builders for Crane Island and we’ll be announcing them shortly! 5 breathtaking model homes will begin in July & August.

  • We’re thrilled to announce our new Vice President of Sales, Marketing, and Builder Program/Relations for Crane Island, Mr. John Hillman!!  

  •  We have a shiny new website that is worth a good look. The new site was built with the intention to share the broader story of the land, architectural vision, and sense of community we are creating at Crane Island. Oh yeah, it will also offer Communication Is Very Important!!  huge variety of comprehensive tools to better understand Crane Island and our real estate offerings! Look for the Interactive Map as it’s pretty darn awesome! 

That’s enough to keep your attention for now and we promise there’s a lot more to come! Please call us, email us, or better yet, come on by and see it for yourself! Crane Island is about to enter a whole new growth spurt with Builders and Residents constructing beautiful homes here in the next 100 days! Come experience and enjoy all that this island paradise has to offer!

Warm Regards, 

The Crane Island Team – Nicole, Vann & John

Images & Videos From April

MORE STORIES TO ENJOY

Porch Stories – 2021 – Sarah Alice Home

Porch Stories – 2021 – Sarah Alice Home

[dipl_double_color_heading heading_main_part="INTRODUCTION" _builder_version="4.9.4" _module_preset="default" main_header_font_size="30px" width="80%" width_tablet="100%" width_phone="100%" width_last_edited="on|phone" module_alignment="left"...

Progress – September 2019

Progress – September 2019

The Backyard - Amelia & Fernandina  Beach September 2019  - Crane Island - Fernandina Beach Florida. As the summer season is winding down, we wanted to reflect on our recent successes and share a progress update about the big things happening on Crane Island this...

2018 End of Year Summary

2018 End of Year Summary

Progress Update - 2018 Recap   A Year of Firsts... A Note From Jack Healan, Jr   2018 Recap & Look Ahead Happy New Year and I hope this email finds you well rested and excited about the year ahead?  I know at Crane Island we sure are.  As we begin 2019,...